A Winter Walk Along Belmont Creek: What the Restored Stretch of Twin Pines Park Does When It Rains

Rain-damp concrete steps approach a recessed oak front door beside a broad window, pale stucco, a mature oak and three sword ferns.

In the summer of 2025, the crew rebuilding Belmont Creek in Twin Pines Park was working against a fixed date. Work started on June 15. Then the crew found archaeological resources in the project area, and the job stopped for about six weeks. Under the environmental permits, all work inside the creek had to be finished by October 15. The city's closeout report says crews worked extended shifts after construction resumed and still finished on schedule.

The deadline closed the dry-season window for in-creek work. The restored stretch reopened to the public in early December 2025, so this is its second rainy season. The designers expected storms to keep shaping the channel after the crews left. That makes a walk after a good rain the best way to see what Belmont built.

A channel designed to be shaped by storms

The project's environmental review lays out the approach. The plans call for constructed riffles at two spots in the creek. A riffle is a stretch where shallow, fast water runs over cobbles and gravel and keeps carrying sediment downstream. Engineers sized the rock by modeling how the channel would behave in design storms. They wanted riffles that would hold up in big flows, because riffles made of the creek's old silt and fine gravel would wash out.

The rocks are also meant to stay small enough to let the creek keep working on its own. The same document says the riffle design "would not use boulders so large that it would prevent natural sediment dynamics and vegetation establishment over time." In other words, the plan expects winter flows to keep moving material around, and Belmont is still in that early period.

Here are the main features in the channel and what the city's environmental review says each one is for:

Feature in the channel What it is designed to do
Constructed riffles of cobble and gravel, at two locations Hold the streambed in place and keep sediment moving downstream
Riffle, run and pool sequences Slow the overall flow and store sediment carried in the water
Rootwads, logs, woody debris and boulders in the streambed Add variety to the channel and help pools form
Regraded, replanted banks Stop the erosion that had lowered the creek bed for decades and weakened the banks

The point of all this reaches past the park. Belmont Creek starts in Belmont and runs through the unincorporated Harbor Industrial Area along the San Carlos border before it reaches the Bay. Silt from eroding banks upstream had been settling in that flatter lower stretch, which needs regular dredging. So the logs and riffles you pass in the park are also meant to keep sediment from building up further down the creek.

Where to stand: the Redwood Picnic Area bridge

The restoration covers more than 500 linear feet of creek, both upstream and downstream of the Redwood Picnic Area bridge. That makes the bridge the natural place to start. The city's closeout report includes a photo of the finished work upstream of the pedestrian bridge, showing placed log structures and constructed riffles.

Daniel Matthews, an assistant engineer in Belmont's Department of Public Works, explained the logs to the Parks and Recreation Commission. The San Mateo Daily Journal reported his remarks as construction was finishing:

"The [log structures] will slow down and detain water in the actual park, and the other cool feature they will have as time develops is that they'll prove to be an important habitat space for plants, insects and even small animals within the creek."

The same Daily Journal story says the work included repaved trails along with the logs and riffles. The riffles are meant to create pools that hold water. The habitat Matthews described depends on those pools, so after a storm, look at where the water slows behind the logs.

You will also see the interpretive signs. The city paid $5,160.88 for them through a change order to meet a grant requirement, and they explain the project to park visitors. The project information sign posted during construction covered the watershed, the sediment problem downstream, the native planting, the reshaped channel and the woody-debris habitat.

What is filling in along the banks

Tree work came first. From January to March 2025, the city removed 52 hazardous and non-native trees. The Daily Journal reported that most were blue gum eucalyptus and that about 30 large tree sections were added to the site. Native shrubs and trees are taking their place. Here are some of the species in the riparian planting plan in the environmental review:

  • Trees: coast live oak, California buckeye, big-leaf maple, box elder and willows
  • Shrubs: red-osier dogwood, creek dogwood, toyon, coffeeberry, spice bush, ceanothus and coyote brush
  • Low growers and grasses: Douglas iris, yerba buena, hummingbird sage, deergrass, Dudley's sedge and California grape

Plantings from late 2025 are still young, and the plan relies on time. The city says it will monitor and maintain the site for five years to make sure the project meets its goals. If you walk the bridge every winter, you can watch the banks fill in over that period.

Why the bill grew, and what is next to it

The project started as a $1 million Urban Streams Restoration grant from the California Department of Water Resources, plus $600,000 split among Belmont, San Carlos and San Mateo County. In November 2024, the city council approved an amendment that raised the three agencies' combined share to $2,265,000. The construction contract went to Hanford Applied Restoration and Construction, and Restoration Design Group designed the work. After three change orders, the construction contract alone came to $2,034,023.14. That figure does not include design or construction management.

The largest change order, $198,943, expanded the restoration so it would meet the mitigation requirements of a separate project, the Belmont Creek Detention Basin. The city describes the basin as an underground stormwater storage facility planned beneath Twin Pines Park parking areas, just downstream, to reduce peak flows in storms. The creek work in the park is already finished, and part of it was built with that basin in mind.

The site's history is also part of what slowed construction. Belmont's environmental review had already recorded a prehistoric archaeological site within the project area, near the Redwood Picnic Area.

Pairing a creek walk with the park's December calendar

Twin Pines Park is open daily from sunrise to sunset. The Belmont Historical Society, Belmont Parks and Recreation and the Senior and Community Center are all in the park, so the creek walk is easy to combine with other stops. Here is what's coming up this season, in order:

  1. Anytime, Wednesday through Sunday, 1 to 4 p.m.: The Twin Pines Art Center is in the Manor House, built in 1908. According to Palo Alto Online's Belmont centennial guide, it has 11 resident artist studios and monthly rotating exhibits that are free and open to the public.
  2. Saturday, December 5, 9 a.m. to noon: The Winter Wonderland Workshop is at Twin Pines Lodge, 40 Twin Pines Lane, for kids ages 5 to 12. It includes ornament-making, cookie decorating, letters to Santa and hot cocoa. Registration closes Friday, December 4, at noon.
  3. Monday, December 7: Last day to send Letters to Santa, according to the city's holiday events page.
  4. Thursday, December 10: Santa at the Firehouse & Toy Drive, plus a Sensory Santa at the Firehouse session.
  5. Thursday, December 17, 5 to 8 p.m.: The Belmont Police Santa Parade.
  6. Sunday, January 10, 2027, 1 to 4 p.m.: The Belmont Historical Society History Room reopens at the back of the Manor House.

The workshop on December 5 makes an easy morning plan. Drop the kids at the lodge, walk to the Redwood Picnic Area bridge, and if it rained earlier that week, see how the water is moving through the riffles.

If you'd like to talk through what's changing around Twin Pines Park and central Belmont, or what those changes mean for a home nearby, Ektra Real Estate is happy to help. Get Your Home Valuation, and we'll walk you through it.

Work With Us

We are proud to have helped so many in their journey here, and we value the trust our client's place in our relationships. Come join us to start your home journey!

Follow Me On Instagram